If 90 men can do a certain job in 16 days, working 12 hours per

Previous Year Papers

Download Solved Question Papers Free for Offline Practice and view Solutions Online.

Test Series

Take Zigya Full and Sectional Test Series. Time it out for real assessment and get your results instantly.

Test Yourself

Practice and master your preparation for a specific topic or chapter. Check you scores at the end of the test.
Advertisement

 Multiple Choice QuestionsMultiple Choice Questions

51.

A can do a certain work in 12 days. B is 60% more efficient than A. How many days will B and A together take to do the same job?

  • 80 over 13
  • 70 over 13
  • 75 over 13
  • 75 over 13
742 Views

52.

A does one-fifth of a work in a week. B finishes the same in a fortnight. B starts the work and works only for 3 days. Thereafter A completes the job. He will finish it in

  • 10 days

  • 7 days

  • 12 days

  • 12 days

736 Views

53.

A can complete a piece of work in 12 days. B is 60% more efficient than A. The number of days, that B will take to complete the same work is

  • 6

  • 7 1 half
  • 8

  • 8

138 Views

54.

A and B together can complete a piece of work in 12 days and B and C together in 15 days. If A is twice as good a workman as C, then in how many days will B alone complete the same work?

  • 30

  • 25

  • 24

  • 24

143 Views

Advertisement
55.

4 men and 6 women together can complete a work in 8 days while 3 men and 7 women together can complete it in 10 days. 20 women working together will complete it in

  • 36 days

  • 32 days

  • 24 days

  • 24 days

139 Views

56.

A and B can do a given piece of work in 8 days, B and C can do the same work in 12 days and A, B, C complete it in 6 days. Number of days required to finish the work by A and C is

  • 16

  • 8

  • 12

  • 24

193 Views

Advertisement

57.

If 90 men can do a certain job in 16 days, working 12 hours per day, then the part of that work which can be completed by 70 men in 24 days, working 8 hours per day is

  • 1/3

  • 2/3

  • 7/9

  • 5/8


C.

7/9


292 Views

Advertisement
58.

A, B and C can do a work separately in 16, 32 and 48 days respectively. They started the work together but B left off 8 days and C six days before the completion of the work. In what time is the work finished? 

  • 10 days

  • 9 days

  • 12 days

  • 12 days

902 Views

Advertisement
59.

A and B can do a piece of work in 30 and 36 days respectively. They began the work together but A left after some days and B finished the remaining work in 25 days. After how many days did A leave?

  • 10 days

  • 6 days

  • 5 days

  • 5 days

148 Views

60.

P and Q together can do a job in 6 days. Q and R can finish the same job in 60 over 7 days. P started the work and worked for 3 days. Q and R continued for 6 days. Then the difference of days in which R and P can complete the job is

  • 15

  • 10

  • 8

  • 8

484 Views

Advertisement