SSCCHSL Important Questions of Time and Work | Zigya

Previous Year Papers

Download Solved Question Papers Free for Offline Practice and view Solutions Online.

Test Series

Take Zigya Full and Sectional Test Series. Time it out for real assessment and get your results instantly.

Test Yourself

Practice and master your preparation for a specific topic or chapter. Check you scores at the end of the test.
Advertisement

 Multiple Choice QuestionsMultiple Choice Questions

Advertisement
1.

A can complete a piece of work in 2 days, and B in 3 days. With the help of C they together completed it in one day. C alone could complete the work in

  • 4 days

  • 5 days

  • 6 days

  • 6 days

144 Views

2.

Amar can complete 1 fourth of a work in 3 days and Shankar can complete 1 over 6 of the same work in 4 days. How much will Amar get if both work together and are paid Rs. 1,800 in all?

  • Rs. 600

  • Rs. 1000

  • Rs. 1080

  • Rs. 1080

125 Views

3.

30 workers can complete a job in 36 days. After 30 days, some more workers joined and the job was completed 2 days earlier. How many new workers joined?

  • 13

  • 15

  • 17

  • 17

217 Views

4.

P takes 5 hours more than Q to complete a work. Working together they completed the work in 6 hours. Q alone could complete the work in

  • 8 hours

  • 10 hours

  • 12 hours

  • 12 hours

144 Views

Advertisement
5.

A can complete a piece of work in 36 days, B in 54 days and C in 72 days. All the three began the work together but A left 8 days before the completion of the work and B, 12 days before the completion of the work. Only C worked upto the end. In how many days was the work completed?

  • 24

  • 25

  • 27

  • 27

223 Views

6.

A and B can do a piece of work in 15 days. B and C can do a similar work in 12 days and C and A in 10 days. How many days will A take to do the work by himself?

  • 13

  • 24

  • 40

  • 40

134 Views

7.

A and B can do a piece of work in 45 and 40 days respectively. They began the work together but A left after some days and B finished the remaining work in 23 days. A left after

  • 6 days

  • 9 days

  • 12 days

  • 12 days

109 Views

8.

2 men and 1 woman can complete a piece of work in 14 days while 4 women and 2 men can do the same work in 8 days. If a man gets Rs. 180 per day, then a woman will get per day

  • Rs. 150

  • Rs. 140

  • Rs. 120

  • Rs. 120

166 Views

Advertisement
9.

A carpenter can build a cupboard in 60 hours. After 15 hours he takes a break. What fraction of the cupboard is yet to be built?

  • 0.5

  • 0.9

  • 0.75

  • 0.25


10.

A works twice as fast as B. If B can complete a piece of work independently in 12 days, then what will be the number of days taken by A and B together to finish the work? 

  • 4

  • 6

  • 8

  • 18

704 Views

Advertisement